Yes, if the deck is more than 0.6 m (2 ft) above the ground: Whitby requires a building permit for it. A lower deck needs no permit but must still meet the zoning by-law's setbacks.

We prepare and submit your permit drawings to the Town of Whitby, then build to the approved plan.

Free Estimate

Get your Whitby deck permit handled.

Takes about 30 seconds. We reply within one business day.

Timeline

No obligation. We never share your details.

Prefer to talk? Call 437-241-6287

Do you need a permit?

Deck permit rules in Whitby.

Whitby draws its deck line at 0.6 m (2 ft) above the ground. On walk-out and sloping lots, including those falling toward the Lynde and Pringle Creek valleys, a main-floor deck often sits well above that, so it needs a building permit and drawings that meet the Building Code. Setbacks come from two 1960s zoning by-laws, 1784 for the former Township and 2585 for downtown, plus a separate Oak Ridges Moraine by-law, and many zones and site-specific exceptions set their own deck rules. Deck applications go through the Town's E-Portal or in person, not by email, and every package is pre-screened.

Checked against the Town of Whitby's own by-laws and pages in November 2026. Rules change, so we confirm them for your address before we draw.

What the city asks for

The Whitby application.

Issued by: Town of Whitby, Building Services Division. We put the package together, submit it and keep you posted.

Documents

  • Application to Construct or Demolish form
  • Schedule 1: Designer Information
  • Applicable Law Checklist
  • Letter of Authorization, if applicable
  • Site plan: property lines, existing structures and setback dimensions
  • Scaled drawings: framing plan, foundation plan, cross section, guard details and construction notes
  • Engineer's design for anything outside Part 9, such as helical piles
  • CLOCA permit, if the lot is in a regulated area
Town of Whitby, Building Services Division: official page

How it goes

  1. 1We measure the yard and deck height and check your zone's deck rules, plus CLOCA and heritage status.
  2. 2We draw the site plan, framing and foundation plans, cross section and guard details to scale, as flattened, unprotected PDFs.
  3. 3We submit through the Town's E-Portal; staff pre-screen the package, then email next steps and the fee invoice, payable by credit card.
  4. 4We answer any review comments until the permit is issued.
  5. 5We book each inspection on the Town's online request form as we build; requests in by 3 p.m. can be scheduled for the next business day.
Processing time
Whitby doesn't publish a deck review time. Every application is pre-screened first; once it's accepted, the Town emails next steps and the fee invoice. For a house with no dwelling unit above another, the Building Code gives the Town 10 business days from a complete application to issue or refuse the permit.
Inspections
The Town inspects at key stages of construction but doesn't list deck stages. The Building Code's required notices include readiness to construct footings and substantial completion of structural framing. Book with the Building Inspection Request form (permit number, site address, inspection type, site contact); requests received by 3 p.m. can be scheduled for the next business day.

Deck drawing — framing plan — Framing plan, section through the deck and elevation. Illustrative sample sheet. Click to enlarge.

Deck drawing — elevations & details

Permit drawings included

We prepare and submit your permit drawings.

A site plan with setbacks, a framing plan, a section through the deck, and footing, guard and stair details, drawn to the Town of Whitby's checklist and submitted with your application.

  • Dimensions to your lot lines
  • Materials, sizes and spacing
  • Footing and base sections
  • Code notes for the inspector
How our drawings work

Decking · real projects

Recent decking jobs across the GTA.

Real Reformity jobs from our project files. Customer addresses are never published.

Whitby deck permit FAQ

Quick answers.

Not if it's under 0.6 m (2 ft) above the ground, but it must still meet zoning. Under the general rules it stays 1.0 m from the interior side and rear lot lines and 3.0 m from a street line (1.0 m in a rear yard), or 0.25 m from the interior side lot line when it's in the side yard beside the house. Some zones differ, so we check yours.

Yes, within the Fence By-law's limits: no privacy screens in front yards, and in side and rear yards a screen must be at least 0.6 m from side and rear lot lines, no more than 2.63 m above grade and no more than 6 m long in total. On a raised deck, the deck and screen together can't exceed 3.5 m.

Yes. Whitby's general zoning lets decks and steps around a pool be up to 1.5 m high: those 0.6 m or lower stay 1.0 m from rear and side lot lines, and higher ones 2.0 m. A deck over 0.6 m needs a building permit, and the pool itself still needs a pool enclosure permit.

Send the form on this page or call 437-241-6287. We reply within one business day, visit to measure, prepare the drawings for the Town of Whitby, submit the application and give you a fixed written price for the work.

Let us handle the Whitby permit.

We measure, draw it to the Town of Whitby's rules, submit the application and build to the approved plan. One business-day reply.

Free Estimate

Book my Whitby site visit.

Takes about 30 seconds. We reply within one business day.

Timeline

No obligation. We never share your details.

Prefer to talk? Call 437-241-6287